Week 17 of Programme

We are now at the end of week 17 on site at Mandeville Primary School where ground beams have been installed to 60% of the building with the first concrete pour completed today.
Works completed so far have included the site set up, new construction entrance, temporary car park, reduced dig, 99No piles, foul and storm drainage including attenuation tank.