Skip to main content

Estuary View, Whitstable

Another busy week on site at Whitstable working alongside Graham Land & Developments. We have almost completed week 54 of our 85 week programme.

External works that are currently being completed are roof coverings, external blockwork and utilities being bought onto site.

Internal works include Blockwork partitions, Blockwork to lift shafts, Metal stud work to En-suites, first fix of the following: Electrical Installation, Mechanical Installation, AC Installation, Sprinkler Installation, Hoist Installation and Medical Gas Installation.