The Apex team on site have been hard at work as they reach a milestone in the project. Collaborating closely with CPC & Ayrshire Metals Ltd, we've successfully completed the steel frame erection phase in 6 days, putting us on schedule as we enter week 14 of 27 on programme. Our attention now turns to the commencement of the 1st fix electrical works, paving the way for the upcoming cladding installation next week with Rhino Exteriors Ltdand the roof installation in the first week of June. Stay tuned to see the progress of the construction skills facility.